| |
|
SECTION
12: Asbestos
Asbestos was incorporated into a number of widely used products, many
of which were used in building construction beginning in the late 1800’s.
By the mid-1980’s, most products
containing asbestos were removed from the market. The most common use of asbestos
in Princeton University buildings was in floor tiles, mastic, thermal
systems insulation (TSI), ceiling tiles, structural steel fireproofing,
and acoustical and decorative plaster.
Asbestos abatement is regulated by the federal Occupational
Safety and Health Administration (OSHA). Abatement in educational
facilities (including most Princeton University buildings) is also
regulated by the New Jersey Departments of Environmental
Protection and Community
Affairs.
Per the OSHA Asbestos Standard (29 CFR 1926.1101), building
materials installed prior to 1980 must be presumed to contain asbestos unless
historical information or testing indicates otherwise. A list of
products that might contain asbestos is included in Appendix
A.
- Prior to building maintenance or renovation projects,
the Project Manager is responsible for arranging a survey
to determine if asbestos-containing building material is present in the work
area and, if so, whether it will be
impacted by the planned work. Contact the EHS Technical Specialist at 258-6251
for testing. The Facilities
Manager of Environmental Compliance or Manager of Alarms/Mechanical Trades
may provide advice and coordination
for asbestos removal projects. Larger scale projects may require an outside
firm to test and design abatement.
- Buildings built prior to 1981 may have asbestos warning
notices on the back of mechanical room doors. The
notices consist of an initial warning that the building may contain
asbestos-containing materials (ACM), a list of
products which may contain asbestos and a notice which lists the results
of previous sampling performed in the
space.
- Asbestos does not always need to be removed if it will
not be disturbed. In some cases, management in place may be advisable.
- If abatement is needed, state regulations require submission
and approval of an asbestos abatement design, use of a state-licensed
firm to perform the abatement, air monitoring at the perimeter of
the abatement area during
removal and inspection and clearance testing of the abated area prior to
re-occupancy. In most cases, an outside contractor performs each of these
functions.
- Under no circumstances shall University or contracted
workers damage or disturb known or suspect asbestos-containing materials
(ACM) unless they are a licensed asbestos abatement contractor and
have been specifically employed to perform asbestos repair or removal.
- If suspect asbestos materials are discovered during the
course of the work, the Project Manager should suspend work that
could disturb the material and contact EHS for testing of the materials.
- The Project Manager should ensure contractors are informed
of the location of suspect and known ACM and that materials which
might be impacted by the work have been abated.
- ACM must be disposed in a secure landfill in a manner
consistent with relevant state and federal regulations.
- Some projects may indirectly disturb ACM. For example,
where asbestos is sprayed on the structural beam above the ceiling
tiles, small amounts of ACM may loosen and fall onto the surface
of the ceiling tile. To avoid personal exposure
or building contamination, a licensed asbestos abatement contractor
must clean the surface of the ceiling tiles before they are
removed or displaced. Contact EHS or the Facilities Manager of Environmental
Compliance
for advice in such situations.
Appendix A: Examples of Products that May Contain Asbestos (top)
Subdivision |
Generic Name |
Asbestos (%) |
Dates of Use |
Binder/Sizing |
Friable
insulation
material |
Spray-applied Insulation |
1 - 95 |
1935-1970 |
Sodium silicate,
portland cement,
organic binders |
Preformed
thermal
insulating
products |
Batts, blocks, and pipe covering
85% magnesia
calcium silicate
|
15, 6 - 8 |
1926-1949
1949-1971 |
Magnesium carbonate
Calcium silicate |
Textiles |
cloth [ 1] , fire blankets |
100 |
1910-1980 |
none |
|
Felts:
Blue Stripe
Red Stripe
Green Stripe |
90 - 95
80
90 |
1910-1980
1910-1980
1910-1980 |
Cotton/Wool |
|
Sheets |
50 - 95 |
1920-1980 |
Cotton/wool |
|
Cord, rope, yarn |
80 - 100 |
1920-1980 |
Cotton/wool |
|
Tubing |
80 - 85 |
1920-1980 |
Cotton/wool |
|
Tape/strip |
80 - 85 |
1920-1980 |
Cotton/wool |
|
Curtains (theatre, welding) |
60 - 65 |
1945-1980 |
Cotton |
Cementious concrete-like products |
Extrusion panels:
Corrugated
Flat
Flexible
Flexible perforated
Laminated
Roof tiles |
8
20 - 45
40 - 50
30 - 50
30 - 50
35 - 50
20 - 30 |
1965-1977
1930-1980
1930-1980
1930-1980
1930-1980
1930-1980
1930-1980 |
Portland cement |
|
Clapboard and shingles
Clapboard
Siding shingles
Roofing shingles |
12 - 15
12 - 14
20 - 32 |
1944-1945
unknown-1980
unknown-1980 |
Portland cement |
|
Pipe |
20 - 15 |
1935-1980 |
Portland cement |
Paper products |
Corrugated:
High temperature
Moderate temperature |
90, 35 -70 |
1935-1980
1910-1980 |
Sodium silicate
Starch |
|
Indented |
98 |
1935-1980 |
Cotton and organic |
|
Millboard |
80 - 85 |
1925-1980 |
Starch, lime, clay |
Roofing felts |
Smooth surface |
10 - 15 |
1910-1980 |
Asphalt |
|
Mineral surface |
10 - 15 |
1910-1980 |
Asphalt |
|
Shingles |
1 |
1971-1974 |
Asphalt |
|
Pipeline |
10 |
1920-1980 |
Asphalt |
Compounds |
Caulking putties |
20 |
1930-1980 |
Linseed Oil |
|
Adhesive (cold applied) |
5-25 |
1945-1980 |
Asphalt |
|
Joint compound |
|
1945-1975 |
Asphalt |
|
Roofing Asphalt |
5 |
Unknown-1980 |
Asphalt |
|
Mastics |
5-25 |
1920-1980 |
Asphalt |
|
Asphalt Tile Cement |
13-25 |
1959-1980 |
Asphalt |
|
Roof Putty |
10-25 |
Unknown-1980 |
Asphalt |
|
Plaster/stucco |
2-10 |
Unknown-1980 |
Portland cement |
|
Spackles |
3-5 |
1930-1975 |
Starch, casein |
|
Sealants (fire/water) |
50-55 |
Sealants (fire/water) |
Castor oil or
polyisobutylene |
|
Cement, insulation |
20-100 |
1900-1973 |
Clay |
|
Cement, finishing |
55 |
1920-1973 |
Clay |
|
Cement, magnesia |
15 |
1926-1950 |
Magnesium Carbonate |
Asbestos ebony
products |
|
50 |
1926-1950 |
Portland cement |
Floor tile and
sheet goods |
Vinyl/asbestos floor tile
Asphalt/asbestos |
21, 26-33 |
1950-1980
1920-1980 |
Polyvinylchloride
Asphalt |
|
Sheet goods, resilient |
30 |
1950-1980 |
Dry oils |
Wall Covering |
Vinyl wallpaper |
6-8 |
Unknown-1980 |
... |
Paints and
coatings |
Roof coating |
4-7 |
1900-1980 |
Asphalt |
|
Air tight |
15 |
1940-1980 |
Asphalt |
[1] Laboratory aprons, gloves cord, rope, fire blankets, and curtains may be
common.
Last
Page Next
Page
|